A SERIES of road closures will be in place for four weeks as highway resurfacing works take place.

Phased closures will be in place in Ashley Road and Christchurch Road to allow contractors to carry out the work.

Starting on February 28, Ashley Road, from Christchurch Road roundabout to the exit junction of Boscombe Bus Station. The closure will last until March 1.

Ashley Road will then be closed from the same roundabout to Browning Road until March 9.

Phase three will see Christchurch Road close from Crabton Close Road to Warwick Road. The closure will be in place from March 10 to March 15.

Christchurch Road, from Parkwood Road to Seabourne Road, will then be closed from March 16 to March 21 for phase four of the works.

Between February 28 and March 7, the one-way traffic order in Haviland Road will be suspended.

Full emergency services access will be maintained and a diversion will be signposted.